Progress of completing mine survey and clearance in Quang Binh and Binh Dinh in 2020

Thứ ba, 22/09/2020

As of June 2020, land in selected districts and communes in Quang Binh and Binh Dinh provinces has been surveyed and cleared for human development and local livelihoods.

 
Progress of completing mine survey and clearance in Quang Binh and Binh Dinh in 2020

The forces implementing the survey and mine clearance work at the Quang Binh and Binh Dinh construction sites in 2018 focused on surveying 21 teams. In 2019: 21 survey teams, 64 clearance teams. In 2020: The technical survey activity will be completed in April 2020 and the focus of technical survey teams to clear the total clearance teams is 85 teams.

Up to now, the surveyed area completed for the whole project by the beginning of June 2020 is 16,880 ha. Clearance area completed by the whole project as of early June 2020 is: 5,194 ha.